Project Capsule: ComEd Illinois

ComEd Illinois

NT IL TSS189 CREGO ROAD

DEKALB, IL * FEBURARY - MARCH 2021
CUSTOMER: LINDBLAD/COMED
PROJECT VALUE: 2.175 MILLION
SCOPE:
• 313 TOTAL FOUNDATIONS
• NEW COMED SUBSTATION FOR FACEBOOK DATA CENTER
PROJECT HIGHLIGHTS
• PROJECT COMPLETED IN 20.5 DAYS
INCLUDING 142 HOLES DRILLED AND POURED IN 5.5 DAYS
• PROJECT WAS COMPLETED WITH ZERO INCIDENTS
• ZERO QUALITY DEVIATIONS
• FULL ENVIORNMENTAL COMPLIANCE

NT IL L15515 Rock Falls Rebuild

HARMON, IL * DECEMBER 2020 – JANURAY 2021
CUSTOMER: COMED
PROJECT VALUE: 1.250 MILLION
SCOPE:
• 35 TOTAL FOUNDATIONS
DIAMETERS OF FOUNDATIONS VARIED FROM 6 TO 9 FEET
PROJECT HIGHLIGHTS
• PROJECT COMPLETED WITH ZERO SAFETY INCIDENTS
• ZERO QUALITY DEVIATIONS
• FULL ENVIORNMENTAL COMPLIANCE

Posted in Project Capsules.